PECAT Flange Adaptor Aids Bellshill Decommissioning Project

As part of a recent project to decommission a transmission reduction station at Bellshill, a new medium-pressure gas main was constructed and commissioned between SGN’s medium-pressure network and the station outlet.

A bespoke WASK 180mm SDR17 × 10″ 150 PECAT flange adaptor was installed to form the tie-in connection to the station outlet. The commissioning of the new main enabled the transmission reduction station to be physically disconnected from the network, allowing the asset to be fully decommissioned.